Sekisui House

Frasers Property

November 2011

    CONSTRUCTION UPDATES NOVEMBER 2011

    ONE CENTRAL PARK

    • Concrete pouring on a large scale is continuing at One Central Park, rapidly escalating after the complex podium levels were completed.

    PARK LANE

    • Watpac has been appointed to build Park Lane, following completion of initial works to basement levels. Construction of the basement parking levels is now underway and it is currently anticipated that we'll reach the ground level of 1-5 Park Lane in January.

    CHIPPENDALE GREEN and INFRASTRUCTURE

    • Work on the new intersection on Broadway at Balfour Street is now underway. Broadway will be widened to accommodate a new turning lane from Broadway into Balfour Street, with the footpath narrowed on the northern side of Broadway. Disruption to traffic and pedestrians is generally scheduled during the evening, and will continue for 4-5 months under close supervision by the NSW Transport department. For more, click here.
    • Stage 1 & 2 infrastructure works, including works to surrounding roads and construction of the road which loops around Chippendale Green, are underway by Christies Civil.
    • Frasers is awaiting finalisation of landscape details from the City of Sydney, which is delaying commencement of landscape works. Consequently, the park is now likely to open in early to mid 2012.

    KENSINGTON LANE

    • Frasers is working with Tonkin Zulhaika Greer to refine the masterplan and undertake design development for the adaptive re-use of heritage buildings in this street, and to design new buildings. Frasers anticipates submitting PAs to the Department of Planning in early 2012 for the majority of the future Kensington Lane precinct.